In Scrum, what is the maximum duration for a sprint?

One week

One month

In Scrum, the maximum duration for a sprint is one month. This time frame is established in the Scrum Guide, which is a formal document created to outline the Scrum framework. The rationale behind limiting the sprint length to a maximum of one month is to provide regular opportunities for teams to deliver incremental value, reflect on their progress, and adapt their work processes. Shorter sprints allow for more frequent feedback from stakeholders and facilitate more adaptability to change, which is a core principle of Agile methodologies.

While sprints can be as short as one week or two weeks, having a maximum duration of one month ensures that teams are not overwhelmed and can maintain a sustainable pace of work. This duration also supports the iterative nature of Scrum, allowing teams to build potentially shippable products with regular intervals of review and improvement.

Get further explanation with Examzify DeepDiveBeta

Three months

Two weeks

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy