What term describes a short, time-boxed period in which a team works to complete a set amount of work?

  1. Iteration

  2. Sprint

  3. Phase

  4. Cycle

The correct answer is: Sprint

The term that describes a short, time-boxed period in which a team works to complete a set amount of work is commonly referred to as a "Sprint". In Agile methodologies, especially in frameworks like Scrum, a Sprint typically lasts from one to four weeks, during which a specific goal or set of features is pursued. This time-boxed approach allows teams to focus on delivering incremental value and enhances collaboration, adaptability, and continuous feedback. By defining a clear time frame, teams can measure their progress more effectively and adjust their plans based on what they learned during the process. As a result, Sprints foster a rhythm of regular delivery and improvement, ensuring that the team can respond quickly to changes and stakeholder feedback. While "Iteration" may also refer to a similar concept in other Agile frameworks like Kanban, it does not always contain the same structured time-boxing or goals as seen in a Sprint. "Phase" and "Cycle" have different connotations, often implying broader stages in a project rather than those focused, short-term periods to accomplish defined tasks.